CBS NEWS STS-122 STATUS REPORT: 32
Posted: 3:00 PM, 1/8/08
By William Harwood
CBS News Space Analyst
SR-32 (01/07/08): Connector upgrade ready for installation; lab testing continues; station spacewalk on tap
=================================
3:00 PM, 1/8/08, Update: Connector upgrade ready for installation; lab testing continues
An upgraded wiring connector will be ready for installation on the shuttle Atlantis' external tank this week in a bid to eliminate the vexing open circuits that grounded the orbiter twice in December. The upgrade is based on a design change implemented by tank-builder Lockheed Martin in the company's Centaur upper stages in the 1990s, a fix that eliminated similar problems with unmanned Atlas- and Titan-Centaur rockets.
The Centaur veterans called in to modify the shuttle's engine cutoff - ECO - sensor pass-through connector said Monday they were optimistic parallel testing at the Marshall Space Flight Center in Huntsville, Ala., will show the shuttle upgrade will resolve NASA's problem once and for all.
"From my point of view, I certainly appreciated the opportunity to come over and help," said James Whelan, electrical and avionics manager for United Launch Alliance's Atlas operations at the Cape Canaveral Air Force Station. "We are hopeful this is going to help solve this mystery.
"It's pretty cool we get to work across a different group of individuals, across a different group of companies. We came together in a fairly short period of time across a holiday and came up with a design solution and implemented something we're hopeful will solve this problem. For me, it's been a good experience."
Asked how many hours he put in modifying the shuttle connectors with soldered pins and sockets, Kenny Reaume, a senior electrical systems engineer with Lockheed Martin, joked that "I can't tell you. My boss would fire me."
NASA attempted to launch Atlantis on a long-awaited mission to deliver Europe's Columbus research module to the international space station on Dec. 6. But the countdown was called off during fueling when tests indicated intermittent open circuits in the ECO sensor circuitry. Similar problems cropped up during a second launch attempt Dec. 9.
Launch then was retargeted for no earlier than Jan. 10, a buffer intended primarily to ensure holiday time off for the shuttle launch team and to give engineers more time to assess the problem. Program managers later moved the target date to no earlier than Jan. 24, saying actual work to fix the connector, install it and re-apply foam insulation likely would push the flight into early February.
As of this writing, that remains the expectation, with insiders saying the flight could slip to after launch of a Russian Progress supply ship. That flight currently is scheduled for takeoff Feb. 7, but the Russians may be able to move launch up a few days depending on how the repair work plays out.
In the meantime, space station flight controllers are making plans for a spacewalk by Expedition 16 commander Peggy Whitson and Dan Tani toward the end of the month to replace a suspect solar array positioning motor. That work is unrelated to on-going analysis of problems with a massive rotary joint on the right side of the station's main power truss that is needed to turn outboard arrays to track the sun.
Engineers do not yet understand what caused unusual erosion inside the starboard solar alpha rotary joint and there are no immediate plans to attempt any sort of repairs. The spacewalk later this month will be devoted to installing a new motor used to change the pitch of one set of right-side arrays.
The four ECO sensors at the base of the Atlantis' hydrogen tank are part of a backup system intended to make sure the shuttle's main engines don't suck a tank dry after some other problem - a leak, for example, or an improper hydrogen-oxygen mixture ratio - used up propellant at faster than normal rates. An engine running out of hydrogen during normal operation likely would suffer a catastrophic failure.
The 10 wires that carry signals from all four ECO sensors and a 5 percent sensor pass through the same connector in the wall of the external tank. The three-part 37-pin connector (27 pins are not used) features a pass-through fitting with gold-plated male pins on both sides.
Wires from the sensors inside the tank terminate in a female connector inside the tank that is plugged into the male pins of the pass-through. Those pins are imbedded in a glass matrix. A similar female socket plugs into the pass-through on the outside of the tank where the pins are mounted in a Teflon insert.
Based on data collected during a fueling test Dec. 18, engineers believe the problem involves circuit-breaking gaps in pins and sockets on the external side of the feed-through connector when the system is chilled to ultra-low temperatures. They believe the sensors themselves are healthy.
"In my experience, very, very cold (temperature) does weird things to metal," Whelan said. "In some cases it shrinks, then it grows and then it changes. It's always interesting working with cryogenics, that's for sure."
The feed-through plate with the external connector still attached was removed and shipped to the Marshall Space Flight Center for additional testing at cryogenic temperatures. Engineers are hopeful they will see the same sort of continuity problems that cropped up during last month's launch attempts. If so, managers will have higher confidence the issue is, in fact, understood.
Back at the Kennedy Space Center, meanwhile, NASA assembled a team of Lockheed Martin and United Launch Alliance engineers to modify replacement connectors, soldering the external wires to the pins in the feed-through connector. The team modified one set of hardware for eventual installation on Atlantis' external tank (ET-125) and two more sets were sent to Marshall for qualification testing at liquid hydrogen temperatures.
Whelan said in the 1990s, Lockheed Martin ran into problems with its Centaur second stage propellant utilization system. The hydrogen-fueled Centaur stage was designed for use with unmanned Atlas and Titan rocket systems.
"We had a data signature on both a Titan-Centaur and an Atlas-Centaur vehicle that led us to believe that we were seeing some intermittent contact or some loss of continuity in our circuitry in our propellant utilization system," Whelan said. "We found a solution which essentially soldered the sockets to the pins of our interface connector on our tank.
Lockheed Martin engineers decided not to modify the connectors inside the tank. Only the external side of the connector was soldered, the same modification approved for the shuttle hardware.
"We've got all new hardware," Reaume said. "We're actually building these sub assemblies right here at KSC in a lab. We have a crew of folks from New Orleans, Lockheed Martin/Michoud, and we have James Whelan and two of his technicians that did the same repair on Atlas. We're working side by side building these sub assemblies up. We have connector experts and harness-build experts here, technicians that have done this probably close to 30 years combined with all these folks. They're all senior-most people, working side by side with Mr. Whelan and his folks, building up the wires and preparing them.
"We actually have four pieces in work at one time," he said. "We just completed two. Actually, the first flight unit that's going to go up to ET-125 is about 99 percent complete, we're just doing some touch ups on it right now, some final electrical re-test. We have two qualification units that are going to go up to Marshall Space Flight Center for some qualification testing. And we had one other test unit that went up to Marshall Space Flight Center as well."
Flight units will be leak tested under flight pressures and subjected to a 50-power microscopic examination before installation. For Atlantis, the flight hardware will be installed before testing at Marshall is complete. That testing will subject the two qualification units to a minimum of five cryogenic cycles each, according to Steve Swichkow, branch chief of NASA's external tank/solid rocket booster electrical engineering group at KSC.
The new connector hardware is built up by passing the incoming wires "all the way through the connector," Reaume said. "After we slide the wire through, we actually crimp the little sockets on. From there, they're actually soldered to the bulkhead connector. When we reassemble this connector and actually put it into a mated position, it's a lot like ... an air hose. It has the coupling ring that you pull back and you engage and it's got the little ball locks that actually lock, you slide the little coupling ring forward and it locks the hose into place. If you can picture that, it's exactly the same concept. You slide it in, you engage it, the coupling ring slides forward and it locks it into place."
Engineers plan to begin installing the upgraded connector on Atlantis' tank Thursday. Once it is in place, foam insulation will be reapplied. The shuttle's eventual launch date will depend, in part, on how long it takes the insulation to "cure," a process that can be affected by humidity, temperature and other weather issues. One internal estimate shows Atlantis being ready for launch 25 days after the connector hardware installation begins. But given the many variables involved, engineers say it's too soon to say when the shuttle might be ready to fly.
=================================
Just the musings of a humble Spaceport Bartender about the world he finds himself in.
Tuesday, January 8, 2008
Subscribe to:
Post Comments (Atom)
About Me
- spacestevie
- I am interested in CNG vehicles because they are good for the environment and aren't powered by dead Marines. I still have a little hope for the world. Read the musings and enjoy.
Blog Archive
-
▼
2008
(352)
-
▼
January
(95)
- When I was in Texas, they called me a Yankee....
- As you can see....
- From Foreign Policy - 7 Questions: Planning for a...
- From Foreigh Policy - The 10 Commandments of Pundi...
- From Foreign Policy - Downloading: Punishable by ...
- From Foreign Policy - Is "Canadian" the new n-word?
- Reminder - MESSENGER Hi-Resolution Photos and Videos
- Mercury's Violent History
- Mercury - Double Ring Crater
- Mercury - The Great Caloris Basin on Mercury
- Mercury - Topographic Close-up
- Mercury Surface Spectra
- Seeking Information on Mercury’s Mineralogy
- Mercury’s Hydrogen Tail
- Mercury’s Internal Magnetic field
- For those Ann Coulter fans out there
- Now you just know I had to post this one....
- Chemtrails anyone? From Foreign Policy
- From Foreign Policy: How to Steal An Election Wit...
- The Shameful State of the Union.....
- Mercury Shows Its True Colors
- “The Spider” – Radial Troughs within Caloris
- First Laser Altimetry for Mercury
- MESSENGER Mission News - 30 January 2008
- MESSENGER Mission News - 29 January 2008
- MESSENGER's Departing Shots
- I love Winter.
- A Closer Look at the Previously Unseen Side
- Mercury's Long Cliffs
- MESSENGER Looks to the North
- Picture perfect - Forest Park, St. Louis
- MESSENGER Mission News
- MESSENGER's Different Views
- Bone CHilling Cold
- Counting Mercury's Craters
- BBC - Paradise in Peril - King Tide Diary
- MESSENGER Dances by Matisse
- First MESSENGER Spectrum of Mercury
- Mercury - in Color!
- The Dick Cheney one is PRICELESS
- Is today the worst day of the year?
- Looking Toward the South Pole of Mercury
- MESSENGER Mission News - January 21, 2008
- News from your bartender.
- Ridges and Cliffs on Mercury's Surface
- MESSENGER Views an Intriguing Crater
- MESSENGER Mission News - January 20. 2008
- First Results from the Mercury Laser Altimeter
- MESSENGER’s First Image after Closest Approach
- MESSENGER Mission News - January 19, 2008
- Another in honor of Martin
- An Overview of Mercury as MISSENGER Approached
- Mercury's Complex Cratering History
- MESSENGER Mission News - January 18, 2008
- MESSENGER Views Mercury’s Horizon
- MESSENGER Mission News - January 17, 2008
- MESSENGER Reveals Mercury's Geological History - R...
- Corporations are EVIL
- MESSENGER Reveals Mercury in New Detail
- Detailed Close-up of Mercury's Previously Unseen S...
- Mercury's Cratered Surface
- How Bush's grandfather helped Hitler's rise to power
- MESSENGER’s First Look at Mercury’s Previously Uns...
- MESSENGER Mission News - The Unseen Side Revealed-...
- MESSENGER Mission News - January 15, 2008
- In Honor of Martin.....
- 31 Similarties Between Hitler and President Bush
- Keeping a Rendezvous with Mercury
- Installing Husband 1.0
- Disney Humor - R rated
- Cthulhu is running for President.
- MESSENGER Mission News (Post Flyby Update)
- Today MESSENGER Flies by Mercury!
- MESSENGER Mission News January 13, 2008
- MESSENGER News from CBS
- MESSENGER News from CBS
- MESSENGER Mission News - The Calm Before CLose App...
- MESSENGER Mission News - January 11, 2008
- Atlantis STS-122 Status Report - 2008 - 11 - 08, 1...
- Life in the City January 11, 2008
- MESSENGER First Picture!
- MESSENGER Mission News 2008 - 01 - 09
- Atlantis STS-122 Status Report - 2008 - 01- 08 15:...
- MESSENGER Mission News 2008 - 01 - 08
- Storm comming in.
- MESSENGER Mission News 2008 - 01-07
- Friday 5 Time Travel.
- Busy day.
- Atlantis STS-122 Launch Status Report - 19:45 EST...
- Just a couple more toons....
- From the Editorial Desk.....
- Wish list for 2008
- My favorite Quotes.
- Benson, its your turn now.....
- Niven's Laws.
-
▼
January
(95)
No comments:
Post a Comment